We are planning on having our data center PDU configured to operate in bystand mode. For this to happen, all systems are being brought down for a couple of hours. We have a SL1 upgraded to Meridian 1 Option 61C Release 24. I do not know if this is a concern or not: the SL1 has an AC power unit in the base, an AC to DC converter power shelf unit on the back; documentation on the 61C upgrade states the unit is DC powered. I have less than 2 wks formal switch training and have been maintaining our system in-house for almost 2 yrs - no vendor support. I saw the posting on shutting down the Opt.61C safely and am using it for a starting point but if anyone has any additional information, it would be appreciated.
Thanks!
Thanks!