bcooler
Programmer
- Jun 13, 2009
- 132
I have an evaluation report I'm creating that shows labor hours as a function of a particular recall. For example, Evaluation 1 has 2 recalls, R-1 and R-2. Let's say each evaluation takes an estimated 1 hour to complete. I'd like to report the total number of hours the evaluation requires (2 in this example) so I can get funding to do the work. Originally, I created the report to show the same hour requirement over and over for each record(multiple listings due to a need to show material needed for a given recall). However, I've moved the hours field into the header area, limiting the hours to one location. Unfortunately, it only shows 1 hour, where the real answer is 2 hours (2 recalls at 1 hour each). I tried to create a sum via the totals query, but had little luck (mostly because I don't know what I'm doing).
How can I ask the report or query to total the needed hours needed?
How can I ask the report or query to total the needed hours needed?