YANKRAY
Technical User
- Nov 7, 2003
- 283
Using MSProjects 2000.
The Duration field shows the number of work days based on the Projects calendar. For example a 3 day duration starting on a friday would show completing on tuesday if the weekends were none work days.
How do I show the calendar days of 5 for the span of Friday through Tuesday in a field? If the field does not currently exist, what is the formula?
Thanks,
Ray
The Duration field shows the number of work days based on the Projects calendar. For example a 3 day duration starting on a friday would show completing on tuesday if the weekends were none work days.
How do I show the calendar days of 5 for the span of Friday through Tuesday in a field? If the field does not currently exist, what is the formula?
Thanks,
Ray