Hi,
Say I have 2 tasks assigned to 1 person. One that takes 9 days, one that takes one day. The one dayer must be done in the middle of the 9 day, so 10 working days total, with the 9 dayer effectively split.
Is there a way of removing that day from the 9 dayer so the resource usage is OK?
Cheers.