Hi
I want to represent a resource calendar whose shift crosses the midnight line. For example, a team works a 12 hour shift starting at 7pm and finishes at 7am next morning.
When I try this, I am told that the shift finish time must be later than the shift start time. This is because it is interpreting these to fall on the same day.
I have tried breaking up the shifts, using non default work hours, a 24 hour format but always hit the same problem.
Any help will be greatly appreciated.
Thanks