Share task to multiple projects

Status
Not open for further replies.

pelagic

Programmer
Nov 7, 2002
97
US
Hi there,

MSProject Resource pool allows multiple projects to share resources.
Does it have the same features for task?
How can I share a task to multiple projects?

Thanks,
 
When you create your master project, put the task in the master project then include the various sub-projects in the master project.
 
Hi PDQBach,

Thank you for your reply. It does work in the application level, but it did not work in the database structure level. Because subproject relate to master project with string and string is very easy to break.
Again, thank you very much for the insight.

Pelagic
 