Hi All,
Here's a problem that's been bugging me for a while, hopefully one of you can help me?
We have 2 requirement types for forecasting (same material number is used for domestic and export sales), a domestic VSF and an export ZVSF, & similarly domestic sales order type and export sales order type.
The domestic sales order type needs to consume the domestic forecast only, and the export S/O type needs to consume the export forecast only.
I have totally separated config for the customer and planned independent requirements, ie I have KSV requirement type on domestic S/Os, and created ZKSV on export S/Os and they each also have different requirements classes (although the requirements classes are configured identically when it comes to the parameters in maintaining requirements classes) and I've set up a new planning strategy/group to link ZKSV-ZVSF, and use strategy 040 for KSV-VSF (standard SAP)
Even with the config separated, either customer requirement will consume either planned independent requirement (ie it consumes the closest according to the consumption periods). Essentially I want the consumption to behave identically for either PIR, but independently of each other.
Here's a problem that's been bugging me for a while, hopefully one of you can help me?
We have 2 requirement types for forecasting (same material number is used for domestic and export sales), a domestic VSF and an export ZVSF, & similarly domestic sales order type and export sales order type.
The domestic sales order type needs to consume the domestic forecast only, and the export S/O type needs to consume the export forecast only.
I have totally separated config for the customer and planned independent requirements, ie I have KSV requirement type on domestic S/Os, and created ZKSV on export S/Os and they each also have different requirements classes (although the requirements classes are configured identically when it comes to the parameters in maintaining requirements classes) and I've set up a new planning strategy/group to link ZKSV-ZVSF, and use strategy 040 for KSV-VSF (standard SAP)
Even with the config separated, either customer requirement will consume either planned independent requirement (ie it consumes the closest according to the consumption periods). Essentially I want the consumption to behave identically for either PIR, but independently of each other.