YANKRAY
Technical User
- Nov 7, 2003
- 283
Using Project 2007.
I have 10 Tasks to perform.
The last task is really the Project and I am trying to reverse schedule the tasks prior to the last to see when the the lastest date is the preliminary work can start.
I want to see this in the calendar with the last task being Day 1 (or Day 0 if Projects calls it that).
These are my tasks:
Issue PO to vendor
Ship part to vendor
Vendor modifies part
Vendor ships part back
Work package is created
Build First Kit
First Kit arrives to customer
Parts arrive to customer
Install team arrives to customer
Kit installation
These tasks are really the project which must start on 8/1.
First Kit arrives to customer
Parts arrive to customer
Install team arrives to customer
Kit installation
These tasks must be completed prior to the above tasks:
Issue PO to vendor
Ship part to vendor
Vendor modifies part
Vendor ships part back
Work package is created
Build First Kit
Each task is the predecessor to the previous task.
I am trying to get MSProject to tell me when I must Issue the PO but as I work backword, the Issue Po to vendor is the driving task.
Hope I made some help and hope someone can help.
Ray
I have 10 Tasks to perform.
The last task is really the Project and I am trying to reverse schedule the tasks prior to the last to see when the the lastest date is the preliminary work can start.
I want to see this in the calendar with the last task being Day 1 (or Day 0 if Projects calls it that).
These are my tasks:
Issue PO to vendor
Ship part to vendor
Vendor modifies part
Vendor ships part back
Work package is created
Build First Kit
First Kit arrives to customer
Parts arrive to customer
Install team arrives to customer
Kit installation
These tasks are really the project which must start on 8/1.
First Kit arrives to customer
Parts arrive to customer
Install team arrives to customer
Kit installation
These tasks must be completed prior to the above tasks:
Issue PO to vendor
Ship part to vendor
Vendor modifies part
Vendor ships part back
Work package is created
Build First Kit
Each task is the predecessor to the previous task.
I am trying to get MSProject to tell me when I must Issue the PO but as I work backword, the Issue Po to vendor is the driving task.
Hope I made some help and hope someone can help.
Ray