Hi there,
I have a project of which there are 2 inserted tasks of holidays and away days inserted under project number. they are all on outline level 1.
when i go to resource usage... it lists people twice- for each mini-project it gives the resource name and if they are over allocated.
I need to link projects (already linked start to start) so that for each resource i.e charli- it will show holidays, away days and project tasks that I am working on. i,e,-
charli - design - 8 hours
holiday - 4 hours
instead of charli - design 8 hours
ben - design 8 hours
andrew - design 5 hours
charli - holiday - 25 hours
so how do i link the projects so that the resources are recognised as the SAME resource? (currently they are linked from my outlook account so no chance that I've clicked on different people!)
many thanks
I have a project of which there are 2 inserted tasks of holidays and away days inserted under project number. they are all on outline level 1.
when i go to resource usage... it lists people twice- for each mini-project it gives the resource name and if they are over allocated.
I need to link projects (already linked start to start) so that for each resource i.e charli- it will show holidays, away days and project tasks that I am working on. i,e,-
charli - design - 8 hours
holiday - 4 hours
instead of charli - design 8 hours
ben - design 8 hours
andrew - design 5 hours
charli - holiday - 25 hours
so how do i link the projects so that the resources are recognised as the SAME resource? (currently they are linked from my outlook account so no chance that I've clicked on different people!)
many thanks