Hello Guys,
How do you change the view page of the resourse usage page to months. The calender you see when you click on the resource page is set as days of the week. How do I display just the number of days in months. I donot want the days in the week display. Any help would be appreciatedc. I am new to MS Project.
richme
 
Double click on the TimeScale across the top of the display.
 