please can anyone tell me if there is a way to make the % units change, when the task type is fixed duration.
What I need to do is see how much extra resource I would need for any given task of a fixed duration. I think...
Alternatively I want Project to say "in order to ensure that none of the 3 resources you have allocated to this task they can work only 10, 35, and 60% on this"
I've tried doing the level resources thang and it refuses point blank, despite pleading, and threatening (this may be something to do with the fact that I've made the tasks fixed duration.
Help - please!
Many thanks
lynne
 