My project contains individual resources and teams set up as resources. Individuals have 80% max unit and teams have 800% max unit allocation.
Here's what I am having a problem with. I have a team (Blue 800%) that has (20+)tasks. Each task has a 1 day duration. Project is showing me that it is going to take the team 20+ days to complete the task. I would expect that of a resource with 100% max unit. For the team with 800% max unit, I expect the finish date to be shorter.
What am I missing? I have attached my project plan for review,if that helps.
Thanks all!
Here's what I am having a problem with. I have a team (Blue 800%) that has (20+)tasks. Each task has a 1 day duration. Project is showing me that it is going to take the team 20+ days to complete the task. I would expect that of a resource with 100% max unit. For the team with 800% max unit, I expect the finish date to be shorter.
What am I missing? I have attached my project plan for review,if that helps.
Thanks all!