Hello All,
Is there a way where I can get Project to push out the duration of a task, dependent on the 'Max. Unit' value for a given resource, when the resource is created on the Resource Sheet.
For example:
On the Resource Sheet (View->Resource Sheet) I create a resource called 'Neal', who has a 'Max. Units' value of 50%.
On the 'Gantt Chart' (View->Gantt Chart) I create a task called 'Task A' with a duration of 2 days. I assign 'Neal' to this task. (he task's duration remains at 2 days.)
I would like Project to increase the duration of the task to 4 days, as Neal is only available for 50% of the time.
I know I can change Neal's working day to be only 4hrs, or create Neal on the Resource Sheet with 100% Max Units then change his Units on the task in Gantt chart to 50% to achieve a change in task duration.
However I would like the 'Max. Units' setting on the resource sheet to be the only time I set Neal's Max Units and this push task duration out.
I appreciate that Project may not have been designed to work this way, however any help or advice would be appreciated.
Many Thanks,
Neal
Is there a way where I can get Project to push out the duration of a task, dependent on the 'Max. Unit' value for a given resource, when the resource is created on the Resource Sheet.
For example:
On the Resource Sheet (View->Resource Sheet) I create a resource called 'Neal', who has a 'Max. Units' value of 50%.
On the 'Gantt Chart' (View->Gantt Chart) I create a task called 'Task A' with a duration of 2 days. I assign 'Neal' to this task. (he task's duration remains at 2 days.)
I would like Project to increase the duration of the task to 4 days, as Neal is only available for 50% of the time.
I know I can change Neal's working day to be only 4hrs, or create Neal on the Resource Sheet with 100% Max Units then change his Units on the task in Gantt chart to 50% to achieve a change in task duration.
However I would like the 'Max. Units' setting on the resource sheet to be the only time I set Neal's Max Units and this push task duration out.
I appreciate that Project may not have been designed to work this way, however any help or advice would be appreciated.
Many Thanks,
Neal