Hi

I've a resource say working for 2 weeks on a task but for 1 day during that 2 weeks I need to assign 50% of his time to another task. how can I do this?

Thanks in advane

Ross

 
Technically:
Create resource
Create tasks
Assign Resource to 2 week task
Assign Resource to .5 day task
View > Resource Usage
Adjust as necessary.

Practically:
Do the first four steps
Make a mental note that Mary won't be available for half a day next Wednesday.
 