For most of my MS Projects (2003) I load the task duration in days but want to really show total hours per task per day especially if there are other projects.
i.e.
A 6 hour task that takes 3 days (2hrs of resource per day)
If I say 6 hours MS Project assumes 8 hrs per day. I cant reset reource work time because the next task(s) might be 6 or 8 hours in one day and so on.
So if I just say 3 days the resource looks over used.
Q> Do I set the time with a forced constraint to maintain my calendar?
What is the best solution?
i.e.
A 6 hour task that takes 3 days (2hrs of resource per day)
If I say 6 hours MS Project assumes 8 hrs per day. I cant reset reource work time because the next task(s) might be 6 or 8 hours in one day and so on.
So if I just say 3 days the resource looks over used.
Q> Do I set the time with a forced constraint to maintain my calendar?
What is the best solution?