Resource leveling

Status
Not open for further replies.

Bellen75

IS-IT--Management
Oct 29, 2009
1
SE
Hi, I wonder, if I have a finish date for a project, a number of tasks to perform, the lenght of the tasks, how do i AUTOMATICALLY allocate the right number of resources to my project? A swift response is much appreciated.
 
You cannot. (30 seconds of reflection will tell you why this cannot happen.)

If the duration is too long then first review tasks on the critical path and reallocate resources assigned to those tasks. Note that shortening the duration of a critical path task may take it off the critical path and put other tasks on the critical path. It is an iterative process.



 