Resource graph shows 100 or 200 % only

Status
Not open for further replies.

jonlykke

IS-IT--Management
May 26, 2011
1
DK
Hi group,

First off: thanks for participating, you guys are cool!

Experince: Newbie enthusiast (with Project course)
Version: Project 2007

I have a problem with my resource graph; all my resources are allocated either 100 or 200% - nothing in between and nothing less than a 100%, which they all should be. Myself (the only 200%) is booked 15.2 hours in June and I'm stilled booked 200 even? My calendar, working time, exceptions etc. is correctly configured.

Can anyone answer me why?

BR

J.
 
Hello J,

Right click on the graph portion -- are you viewing Peak Units? That will show a resources highest assignment level -- even if it is for so much as 1 minute in the time frame.

You might find that "Work" is a more meaningful value instead of Peak units.

Julie
 