Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Mike Lewis on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Resource Graph not updating with work complete

Status
Not open for further replies.

AdamTJ

Technical User
May 17, 2005
21
0
0
US
I am having an issue getting the resource graph to update when we are updating actual / remaining work columns. There is a fair amount of formatting in the schedule, basically using constraints and not predecessors. But when the remaining work goes down, I would imagine that the needed resources would also decline.

I am not sure what other information to provide,

Please let me know,
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top