Here's my situation: I have a task of a particular project that runs for a couple months. I have one resource assigned to this task. At this point the task is about 3wks from completion. The probelm is that the resource assigned to this task has to be used elsewhere, so I need to assign another resource to finish the remainder of the task. In reality, this is no problem, but I can't figure a way to do it in project. Is there a way to assign two resources to a task, but have resource1 work for the first 2/3 of the task at 100%, and resource2 work for the last 1/3 at 100%?
Any help is greatly appreciated, thanks.