We have a customer that we're receiving several PI-BD major alarms. We're going to replace the TN765 board, but is there any pre-replacement steps I should follow? Site is G3v11.

Thanks in advance for any sugesstions.
 
what are the links programmed for?
are the links working or going up and down?

It's rare to have to replace a tn765

links are commonly used for x.25 isdn, cms, audix, dcs


Power down the control cabinet, replace the board, and power the cabinet back up.

A great teacher, does not provide answers, but methods to teach others "How and where to find the answers"

bsh

36 years Bell, AT&T, Lucent, Avaya
Tier 3 for 26 years and counting
 
Tier 3 thanks for the procedure.

Below is some of the error log

01A1 PI-SCI 1025 1
01A1 PI-SCI 3073 13
01A1 PI-SCI 1281 102

Link 4 is used for CLAN 1B16 and there are bx25 links to audix.
 