Hopine someone can help me on this. I am using Project Professional 2003. I have been given a project that has already been created by someone else. Unfortunately they typed in there start dates creating constraints. I need to remove these in order to fix the project. I follow the directions in the help file.
1. click on the name column.
2. open the task dialogue
3. select the advance tab.
4. change the constraint type to As Soon As Possible.
Now, I should be able to increase the duration of a task without any problems. Instead a message box pops up telling me that the task or one it's linked to has a constraint. What gives? I removed them all. How could this be?
As an experiment. I cut and paste the offending tasks into a new worksheet and I don't get the message when I increase the same task's duration.
Is this a bug with Project 2003?
1. click on the name column.
2. open the task dialogue
3. select the advance tab.
4. change the constraint type to As Soon As Possible.
Now, I should be able to increase the duration of a task without any problems. Instead a message box pops up telling me that the task or one it's linked to has a constraint. What gives? I removed them all. How could this be?
As an experiment. I cut and paste the offending tasks into a new worksheet and I don't get the message when I increase the same task's duration.
Is this a bug with Project 2003?