It is the second time I start the Regenerate Material Plan process today and it seems to "freeze" in the Merging Remaining Order section. I waited for more than 1 hour each attempts and I had to manually close the MRP Process Status window. Of course closing this window does not generate anything in the mrreqfil_sql table so I can't run the Requirements by date report. Both attempt stop at the same item. It was working fine last week. What could cause this issue? The only difference between last week and this week is we entered a few sales order.
Thanks for your help
Thanks for your help