GarethWhite
IS-IT--Management
Hi all,
I am attempting to generate a RAG status indicator that shows the following formula:
If task is approaching target completion date (i.e. 20% time from completion date)and the % complete is >80% then the RAG should show green.
If the % complete is between 50% and 80% then show amber and <50% show red.
I would like to use this to be able to see at any point very quickly whether we are at risk of becoming behind schedule by using the above. Can anyone help with the formula?
I am attempting to generate a RAG status indicator that shows the following formula:
If task is approaching target completion date (i.e. 20% time from completion date)and the % complete is >80% then the RAG should show green.
If the % complete is between 50% and 80% then show amber and <50% show red.
I would like to use this to be able to see at any point very quickly whether we are at risk of becoming behind schedule by using the above. Can anyone help with the formula?