"OR" dependency between tasks

Status
Not open for further replies.

AnoNhym

Instructor
Jan 31, 2012
1
CA
Hello,

In MS Project, I have Tasks A, B, C. I want to say that Task C can start when either Task A "OR" Task B has finished. I can only see an "AND" dependency. Is an "OR" dependency possible?
 
Sorry, no. In a predecessor relationship with multiple predecessors it is always the later of the two predecessors.

You can experiment with Inactive tasks if you use Project 2010 Professional.
 