In our MRP reports used for purchasing, we currently see the suggested purchase quantity as a quantity over the min. order quantity. However this misleads us in some cases where we have to purchase the material in the quantity that the supplier packages it in. For example: The supplier packages the material only in 50 lbs boxes. If the demand is 55 lbs, the MRP report suggests a 55 lbs purchase. But in order to complete the 55 lbs demand, we need to order 100 lbs (2 boxes of 50 lbs each). This can lead to incorrect projected cash management issues.
How can the suggested order quantity be forced to be in the increments that the material is packaged in?
How can the suggested order quantity be forced to be in the increments that the material is packaged in?