Hi all,

running epo 3.0.1 on Windows 2000 srv. We have configured to run pull tasks from NAIHttp and NAIFtp every second hour. For example: Pull from NAIHttp 10:00pm, pull from NAIFtp 11:00pm, etc.

They are scheduled _not_ to conflict. We see that the pull tasks stops working after a while. Also we have seen occasionally that the epo-server service stops responding.

SiteMgr.log reports a bunch of "DAL Stack" messages with errorcodes. Restart of server or services seems to remedy for some time, until it appears again.

Env: W2000 srv, sp4. MSDE 2 (sql 7 light), sp4 for sql 7. Checked database for integrity as the "DAL errormessage" would indicate problems connecting to database. Found no problems..

Any ideas?

Regards,

Mikael Fryksten