All,
A simple question, I think... I'm entering tasks into Project 2002. What I want to do is have a number of hours for the taks, say 20, but I want that to cover a 2 week period (10 hours per week). When I enter 20, Project automatically calculates the number of "Days" for that task, and it winds up being 3 days. Is there a way to set this so that Project doesn't force the day calculations based on time?
Many thanks.
Best Regards,
Scott
Please let me know if this has helped
A simple question, I think... I'm entering tasks into Project 2002. What I want to do is have a number of hours for the taks, say 20, but I want that to cover a 2 week period (10 hours per week). When I enter 20, Project automatically calculates the number of "Days" for that task, and it winds up being 3 days. Is there a way to set this so that Project doesn't force the day calculations based on time?
Many thanks.
Best Regards,
Scott
Please let me know if this has helped