Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations IamaSherpa on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Project time over days 1

Status
Not open for further replies.

Scott24x7

Programmer
Jul 12, 2001
2,825
JP
All,
A simple question, I think... I'm entering tasks into Project 2002. What I want to do is have a number of hours for the taks, say 20, but I want that to cover a 2 week period (10 hours per week). When I enter 20, Project automatically calculates the number of "Days" for that task, and it winds up being 3 days. Is there a way to set this so that Project doesn't force the day calculations based on time?

Many thanks.
Best Regards,
Scott

Please let me know if this has helped [hammer]
 
Hi Scott

If I understand you correctly, what you want to do is to have one or more resources carrying out the task for 20 hours during a 2-week period. In that case, make the task type 'Fixed duration', make it 2 weeks long, and assign a resource to it with 20 hours of work.

I'm using Project 98, so knowing Microsoft some of the terminology will have changed, but hope this helps.

Ben
 
Ben,
Well, I tried that, but it is giving me the same result. Either I get the number of hours that I want, but the "Span of days" is wrong, or I get the span of days, but the number of hours is wrong.
(i.e. in this case, I want 20 hours of 2 weeks. If I put in 20 hours, and start on say, July 1, it ends automatically on July 4. If I put in July 1, to July 14, then it gives me 80 hours.) Any other ideas? This should not be this complicated!


Many thanks
Best Regards,
Scott

Please let me know if this has helped [hammer]
 
Ben,
Well, I got what I'm after, with a similar solution. I set the duration to 2 weeks, choose the resource, and then set the % of effort against the task, so if I want them to spend 20 hours on it, I set the % to 25% effort over 2 weeks, which equates to 20 hours work, and calculates my cost of the employee correctly! So, you were on the right track. Thanks for that.

-Scott
Best Regards,
Scott

Please let me know if this has helped [hammer]
 
Hi Scott,

Possibly the solution you are looking for is as follows:
1) Be in the Gantt Chart with the diagram visible
2) Right-click on the bar that shows your duration. It will bring up a menu and select split. Follow its instructions from there.

Regards,
dave
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top