Every Monday morning, my area is responsible for updating all project plans to determine new estimated start and end dates as well as the variance as compared to the baseline. We do this in MSP by using:
'tools'
'tracking'
'update project'
and then selecting 'reschedule uncompleted work to start after (current date)'
and 'entire project'.
Often times when this is done, MSP does not appear to adjust the dates correctly & therefore shows invalid data and variances. It also adds unwanted constraints and changes task durations.
For example, before the work was scheduled, a task had a duration of .25 hours and was set to start and end on the same date (11/2). After updating, the duration changed to .50 hours with a start date of 11/9/04 and an end date of 12/2/04.
Does anyone know why this sort of thing happens?
Is there a better way to update the project plans each week?
'tools'
'tracking'
'update project'
and then selecting 'reschedule uncompleted work to start after (current date)'
and 'entire project'.
Often times when this is done, MSP does not appear to adjust the dates correctly & therefore shows invalid data and variances. It also adds unwanted constraints and changes task durations.
For example, before the work was scheduled, a task had a duration of .25 hours and was set to start and end on the same date (11/2). After updating, the duration changed to .50 hours with a start date of 11/9/04 and an end date of 12/2/04.
Does anyone know why this sort of thing happens?
Is there a better way to update the project plans each week?