Hello,
I've two questions about project management... We're using project server and project pro 2003...
1. When I assign two resources to a task, and one resource increase it's work status %100, the task's status changes to %50. This is ok. But what I want is to see the statuses of resources' status individually. Overall Task:50% - Resource1:100% - Resource2:0%. How can I see this thru project server or from project?
2. How can I assign another project manager to a project? For example I'm the manager of a project for one leg in project and another person is manager in another leg. What I want is we are both project managers, and can see project info in our lists, general status of project and create tasks in project. Is this possible in MSProject logic?
Thanks,
Ali
I've two questions about project management... We're using project server and project pro 2003...
1. When I assign two resources to a task, and one resource increase it's work status %100, the task's status changes to %50. This is ok. But what I want is to see the statuses of resources' status individually. Overall Task:50% - Resource1:100% - Resource2:0%. How can I see this thru project server or from project?
2. How can I assign another project manager to a project? For example I'm the manager of a project for one leg in project and another person is manager in another leg. What I want is we are both project managers, and can see project info in our lists, general status of project and create tasks in project. Is this possible in MSProject logic?
Thanks,
Ali