I have a project set up that I ran earlier in the year. I'm involved in an identical project for one of the other companies in the group and want to use the same project plan. Is there a quick way to simply drag the existing tasks to the new project start date whilst maintaining the links and milestones?
Whenever I've tried to move it in one go, some tasks stay put because they have got firm start dates that can't be moved without going into the task and changing it manually.
Any help greatly appreciated,
Mark.