Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations strongm on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Project 2013 week number discrepancy between screen and print

Status
Not open for further replies.

deesloop

IS-IT--Management
Jul 19, 2013
12
GB
The project is set to Start 06/03/2017
So week 1 in our heads is obviously week commencing 06/03/2017

However some prep work needs done 8 weeks before the project starts in earnest
So we have a task 1a that starts 6 weeks prior to 06/03/2017 eg 09/01/2017

When I add this task the weeks are renumbered so that that week 1 starts when Task 1a starts (09/01/2017) rather than what the project start date is set to (06/03/2017).

However when you preview/print it week 1 is indeed as per the project start date (06/03/201) and task1a is shown to run from -8w to week1

Project 2007 doesn't display this behaviour. On screen shows W1 as being 6/3/2017 and the print/preview matches. The issues is for Project 2013 and have been tried on 3 or 4 machines all displaying the same issue.

How do we get the gantt chart to match the print preview/printout.

I've attached 2 images.
One is a screen shot from within Project
The other is a screen shot after having printed the doc to PDF - however the physical print out matches this.

project_nifv6n.jpg


print_rxprqy.jpg
 
 http://files.engineering.com/getfile.aspx?folder=8d45ffb0-8fe0-4aad-bc21-018a6426a1af&file=print.jpg
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top