FallingRockAhead
Technical User
Simple set up: With MS Project 2007, set up for calculations based on Physical % Complete. Schedule is a cost loaded, baselined schedule. Show (for example) cost1 field set up for summing. Show the baseline cost field and the cost field. Some tasks should have a P%Compl > 0. Copy the Baseline Cost column into the Cost1 field. This will change almost all (but not all) of the Cost field numbers if P%Compl > 0 (and Baseline Cost field does not = Cost field).
Okay, what's this about? It does not seem to affect the EAC, BCWS, BCWP, etc.
Thanks,
Tom
Okay, what's this about? It does not seem to affect the EAC, BCWS, BCWP, etc.
Thanks,
Tom