In my limited configuration I couldn't do a lot of testing.
But, basically, "Not within MS P2002 Pro".
The best I could come up with is
1. put a specific user in charge of corporate Global.mpt
2. that person makes the changes and then emails it to the other PMs
3. Other PMs save it.
The issue is that if you have a calendar XYZ in your project file and there is also a calendar XYZ in Global.mpt then the project file XYZ is used by MSP2002.
You would have to institute a mechanism for making certain that changes to Global.mpt were distributed *and* that the existing project files were properly modified (using Tools | Organizer).