Project 2000 Report Bug Related to Date Format?

Status
Not open for further replies.

davidd31415

Programmer
Jan 25, 2006
154
US
I'm using Project 2000 to generate a "Who does what when" report and have found that the default report (with a date format of 1/31, 2/1, ...) does not show all resource usage. I have resources used for 6 months but the report only shows the next two. If I change the date form to 1/31/00, 2/1/00, ... then it looks like the correct resource usage is shown.

Does anyone know if this bug is documented? I am nervous relying on the report data with the second date format since I already know there are problems with the first one...

Thanks,

David
 
I don't have P2000 on any machines so I couldn't check it specifically but I did look at the output from P2003 and didn't see any variances based on the date (well, technically, I suppose I did: using the longer date format took more pages to print but the actual data was the same regardless of the date format).

I've used WDWW since P98 and never noticed a discrepancy like the one you are describing.

If you continue to be worried, the report output is similar to the Resource Usage display so you could compare the two to see if they are in agreement.
 