Progress bars

Status
Not open for further replies.

Lilliabeth

Technical User
Jan 26, 2005
1,190
US
In the midst of the project, I have entered a status date and want to see the progress line in tracking gantt. I see that tasks have started and finished earlier than the baseline start and finish, yet my progress line points to the left. What am I missing?

--Lilliabeth
 
Hi Lilliabeth,

The position of the progress point is calculated based on
the cumulative percent complete value of the actual plan
task on the status date but it is placed on the baseline
bar if you choose "Display progress lines in relation to
Baseline plan" option.

Hope this helps.

Best Regards,
JNB
 