I have a project that will be starting at 6pm on Friday. This project will be run 24 hours a day until completed. I have changed the Default start time in the Options tab to 6:00pm and the end time to 6:00 pm. Hours per day is 24.
For the Project Information it has a start date of Friday. It is using the 24 hour calendar. I have the working times for the calendar set at 12:00 am to 12:00 am. I can't specify a working time of 6:00pm to 12:00 am and then 12:00 am to 6:00 pm. It has problems with starting the 24 hours with 6:00 pm and wrapping over to the next day.
Help!!!! How can I get my project and subsequently my Gantt chart to start on Friday at 6:00PM?
Thank you for your help.
Tammy
For the Project Information it has a start date of Friday. It is using the 24 hour calendar. I have the working times for the calendar set at 12:00 am to 12:00 am. I can't specify a working time of 6:00pm to 12:00 am and then 12:00 am to 6:00 pm. It has problems with starting the 24 hours with 6:00 pm and wrapping over to the next day.
Help!!!! How can I get my project and subsequently my Gantt chart to start on Friday at 6:00PM?
Thank you for your help.
Tammy