StuartMantel
IS-IT--Management
I am having a problem calculating dates/durations.
For most of the project, I am using the standard calendar (with company holidays added).
One task is a process that will run 24 hours 7 days a week. I created a task to start on 8/21/14 with a duration of 114 days.
The standard calendar calculates the end date to 2/5/15. This is correct for a standard work week.
I assigned the task the 24 hour 7 day week calendar and it calculates the end date to 9/27/14 which is only 36 days.
I created a resource called Process Servers and assigned it the 24 hour calendar. The task has calendar set to None. It still has an end date of 9/27. It should be 12/13/14.
If I enter the duration as 2736 hours (114 X 24) it calculates to 12/13.
Can anyone suggest where I can look to correct this?
Thanks in advance.
For most of the project, I am using the standard calendar (with company holidays added).
One task is a process that will run 24 hours 7 days a week. I created a task to start on 8/21/14 with a duration of 114 days.
The standard calendar calculates the end date to 2/5/15. This is correct for a standard work week.
I assigned the task the 24 hour 7 day week calendar and it calculates the end date to 9/27/14 which is only 36 days.
I created a resource called Process Servers and assigned it the 24 hour calendar. The task has calendar set to None. It still has an end date of 9/27. It should be 12/13/14.
If I enter the duration as 2736 hours (114 X 24) it calculates to 12/13.
Can anyone suggest where I can look to correct this?
Thanks in advance.