Problems after move from Project 2003 to 2007

Status
Not open for further replies.

gicio

Programmer
Jun 18, 2002
39
0
0
DE
Hi!

today I deinstall the Microsoft Project 2003 and install Microsoft Project 2007.
Now I have a big Problem:

when I add to my project plan 3 tasks:
Task1, task2 and Task3, I can connect the three task BUT the task are not move automatically to the end of the last task.

The work flow I make this:

add Task1 on the date: 01.11.2007 duration: 1day

add Task2 on the date: 01.11.2007 duration: 1day

add Task3 on the date: 01.11.2007 duration: 1day

Normally when I connected the three tasks in my project 2003 the tasks change the start day...

In 2003 it would looks like:

Task1 begin at 01.11.2007 duration 1 day
Task2 begin at 02.11.2007 duration 1 day
Task3 begin at 03.11.2007 duration 1 day

This doesn't happen in 2007 :(

all three tasks are on the same day (01.11.2007) after I connect it.

Is it a bug?
What can I do?

Regards,
 
Try Tools / Options / Calculation - change mode to automatic calculation
 