Problem reporting with Who Does What map and Resource Pool

Status
Not open for further replies.

mandim4

Technical User
Apr 22, 2004
1
GB
I've set up multiple projects, all using the one Resource Pool 'project' (following the Microsoft Help). But now when I wish to publish my Who Does What html doc (using the standard who does what map), the tasks are no longer split/grouped by resource. The Who Does What report still works OK.
If I set a project to 'use own resources', the Who Does What map works as before (ie. showing assignments per resource).

I'm just going round in circles now, not sure what to do/try next. Can anyone help please?

I am using Project 2003 - their help doesn't seem to throw any light on the subject. I have a Project 2000 book which doesn't help either.
 