Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Mike Lewis on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Predecessors Not Calculating When Adapting Plan 1

Status
Not open for further replies.

alex20850

Programmer
Mar 28, 2003
83
US
I have a Project Plan that was used for another project and I have zeroed out all the Percent Complete and the Baseline, but when I plug in new Start with the existing Duration, the Predecessors are not calculating. I have shown the project to two other people fairly knowledgeable with Project and they are also puzzled.
 
Autocalc may be turned off. 2 ways to fix. Hit F9 and see if it updates all your dates or go to Tool/Options/Calculation and make sure the "Automatic" radio button is selected under Calculation Mode.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top