Hi
I am a project manager for 5 years. My MS project knowledge is basic. Not very high level. I joined this company where my project's plan is broken down to micro level tasks and runs to 4000 rows.
The problem is the project has predeccessors, successors and other dependencies. The project is very dynamic with tasks changes, resource changes, date changes each week.
Its a nightmare to update it. My question is how to Know the dependencies when i make some change ? Scrolling 4000 lines to identify it is impossible. Example if i change date in row 10 and that changes dates in row 150, 199, 244, 566,880,1458,2678 .. How to know it ???
I am a project manager for 5 years. My MS project knowledge is basic. Not very high level. I joined this company where my project's plan is broken down to micro level tasks and runs to 4000 rows.
The problem is the project has predeccessors, successors and other dependencies. The project is very dynamic with tasks changes, resource changes, date changes each week.
Its a nightmare to update it. My question is how to Know the dependencies when i make some change ? Scrolling 4000 lines to identify it is impossible. Example if i change date in row 10 and that changes dates in row 150, 199, 244, 566,880,1458,2678 .. How to know it ???