Hi:
I hope someone can help with this. I've pasted some values into the Physical % Complete column, but the Outline Level 0 summary task and all summary task fields below it show 0%. In other words, this column is not summing up the values that I pasted below it. How can I get it to do so?
Background: I'm trying to use Physical % Complete to base MS Project's Earned Value fields on % Work Complete instead of % Complete. % Work Complete is a work based calculation of the completeness of a task or a project, while % Complete is a duration based calculation. Earned Value calculations should use % Work Complete. This is a recognized problem with MSP. Microsoft provided the Physical % Complete field to allow users to base Earned Value calculations on other values. (You have to set the Earned Value field on the Tools / Options / Calculations tab to use Physical % Complete.) This is what I did. Then I hid the summary tasks and pasted the % Work Complete task values into the Physical % Complete column (highlight source column, copy, high target column, paste). Then I displayed the summary fields again and found that whereas the % Work Complete column showed a project level value of 96%, the Physical % Complete field showed a project level value of 0%. Why is this and how can I correct it? Also, any recommendations for how to get %Work Complete to display in the Physical % Complete field, so that MSP uses this value for EV calculations, instead of % Complete???? Any help would be greatly appreciated. Thanks in advance for any feedback or suggestions. (By the way, I'm using MSP 2003 Professional both offline and with Project Server.)
Djoliver1
I hope someone can help with this. I've pasted some values into the Physical % Complete column, but the Outline Level 0 summary task and all summary task fields below it show 0%. In other words, this column is not summing up the values that I pasted below it. How can I get it to do so?
Background: I'm trying to use Physical % Complete to base MS Project's Earned Value fields on % Work Complete instead of % Complete. % Work Complete is a work based calculation of the completeness of a task or a project, while % Complete is a duration based calculation. Earned Value calculations should use % Work Complete. This is a recognized problem with MSP. Microsoft provided the Physical % Complete field to allow users to base Earned Value calculations on other values. (You have to set the Earned Value field on the Tools / Options / Calculations tab to use Physical % Complete.) This is what I did. Then I hid the summary tasks and pasted the % Work Complete task values into the Physical % Complete column (highlight source column, copy, high target column, paste). Then I displayed the summary fields again and found that whereas the % Work Complete column showed a project level value of 96%, the Physical % Complete field showed a project level value of 0%. Why is this and how can I correct it? Also, any recommendations for how to get %Work Complete to display in the Physical % Complete field, so that MSP uses this value for EV calculations, instead of % Complete???? Any help would be greatly appreciated. Thanks in advance for any feedback or suggestions. (By the way, I'm using MSP 2003 Professional both offline and with Project Server.)
Djoliver1