Hi all,
I ran into a problem and I was wondering if anyone here can help me.
In a project I am building, there is one task with three resources. The one main resource, I have tried assigning different percentages to, but nothing works.
Let's assume I currently tried putting this resource on 50% (since it's the shortest duration Project would calculate, although still too long). When I assign this resource 100% the task takes actually longer, due to MS Project allocating him almost exclusively in his free days.
I can see on the task usage that this resource is not 100% on every day, and slacks in many of them, however when I try to fill the delta in manually, it doesn't always let me (e.g. say on a certain day, that resource, has only 80% utilization and 0.1 days on the specific tasks, when I try to up this to 0.3, Project wouldn't let me, sometimes. some other times it would, no idea why).
What I would love to do, is allocate this resource to it's max utilization (given he has other tasks), so he will be 100% every day, and that the delta would always be on this specific and pretty long task - Is this possible in any way? Allocating on a delta instead of finding a percentage? I there any other way I can solve this problem.
The real problem by the way, is that due to this under allocation, this task is taking two months too long, I believe that if I were able to assign the delta to this resource, this would be shortened considerably.
Thank you for your help!
I ran into a problem and I was wondering if anyone here can help me.
In a project I am building, there is one task with three resources. The one main resource, I have tried assigning different percentages to, but nothing works.
Let's assume I currently tried putting this resource on 50% (since it's the shortest duration Project would calculate, although still too long). When I assign this resource 100% the task takes actually longer, due to MS Project allocating him almost exclusively in his free days.
I can see on the task usage that this resource is not 100% on every day, and slacks in many of them, however when I try to fill the delta in manually, it doesn't always let me (e.g. say on a certain day, that resource, has only 80% utilization and 0.1 days on the specific tasks, when I try to up this to 0.3, Project wouldn't let me, sometimes. some other times it would, no idea why).
What I would love to do, is allocate this resource to it's max utilization (given he has other tasks), so he will be 100% every day, and that the delta would always be on this specific and pretty long task - Is this possible in any way? Allocating on a delta instead of finding a percentage? I there any other way I can solve this problem.
The real problem by the way, is that due to this under allocation, this task is taking two months too long, I believe that if I were able to assign the delta to this resource, this would be shortened considerably.
Thank you for your help!