Jun 3, 2008 #1 baferrari Technical User Jun 3, 2008 2 GB Is there anyway I can see a report of pending tasks on Microsoft Project?
Jun 3, 2008 #3 PDQBach IS-IT--Management Sep 26, 2003 1,523 US Hee hee ... you probably meant to ask "How can I see a report of pending tasks?" View | Reports | Current Activities | Tasks Starting Soon Click on "Select" Enter date1 and date2 It will display tasks where Finish >= Date1 and Start <= Date2. Or, in other words: if any part of the task is between Date1 and Date2 then it will be reported. Upvote 0 Downvote
Hee hee ... you probably meant to ask "How can I see a report of pending tasks?" View | Reports | Current Activities | Tasks Starting Soon Click on "Select" Enter date1 and date2 It will display tasks where Finish >= Date1 and Start <= Date2. Or, in other words: if any part of the task is between Date1 and Date2 then it will be reported.