pending tasks

Status
Not open for further replies.

baferrari

Technical User
Jun 3, 2008
2
GB
Is there anyway I can see a report of pending tasks on Microsoft Project?
 
Hee hee ... you probably meant to ask "How can I see a report of pending tasks?"

View | Reports | Current Activities | Tasks Starting Soon
Click on "Select"
Enter date1 and date2

It will display tasks where Finish >= Date1 and Start <= Date2.

Or, in other words:
if any part of the task is between Date1 and Date2 then it will be reported.


 