Hi all,
I am a little new to MS Project and still trying to figure things out, but to start with, I have a question.
So I have a project with several tasks and resources - however whenever a task requires more than 1 resource, it allocates all of them for the same time (say 5 man days), whereas I would like to have them allocated for different amounts of time, so that some resources actually spend only 1 hour on that specific task.
And of course, I want to do this automatically.
To elaborate, I first used excel to create work for every task (the sum was 174 man days), than I allocated work for the 21 resources, so that none will exceed 10 man days (2 working weeks). Than I ran all kinds of checks and sumifs in excel to see if everyone is not overallocated - and everything turned out to be perfect. since when there are more than 1 person working at the same task, there could be differences in the time each of them works on the task.
However, when I moved everything to project, things went wrong - people who were scheduled to work for only 1 day on task X, suddenly have to work 4 days, just like the other co-workers on the same task.
The bad result being that instead of duration not exceeding 2 weeks on excel, - on project it definitely exceeds that by a lot.
My goal is to have employees working partially on tasks, even if the task takes longer, and to have the project done within 2 weeks, with perfect allocation.
Is there a way to do it, and what am I doing wrong currently?
Thanks a lot!!
I am a little new to MS Project and still trying to figure things out, but to start with, I have a question.
So I have a project with several tasks and resources - however whenever a task requires more than 1 resource, it allocates all of them for the same time (say 5 man days), whereas I would like to have them allocated for different amounts of time, so that some resources actually spend only 1 hour on that specific task.
And of course, I want to do this automatically.
To elaborate, I first used excel to create work for every task (the sum was 174 man days), than I allocated work for the 21 resources, so that none will exceed 10 man days (2 working weeks). Than I ran all kinds of checks and sumifs in excel to see if everyone is not overallocated - and everything turned out to be perfect. since when there are more than 1 person working at the same task, there could be differences in the time each of them works on the task.
However, when I moved everything to project, things went wrong - people who were scheduled to work for only 1 day on task X, suddenly have to work 4 days, just like the other co-workers on the same task.
The bad result being that instead of duration not exceeding 2 weeks on excel, - on project it definitely exceeds that by a lot.
My goal is to have employees working partially on tasks, even if the task takes longer, and to have the project done within 2 weeks, with perfect allocation.
Is there a way to do it, and what am I doing wrong currently?
Thanks a lot!!