Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations TouchToneTommy on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

P3 Schedule error into Expedition

Status
Not open for further replies.

kinjor

Technical User
Mar 30, 2005
1
US
I am trying to link a P3 schedule with Primavera Expedition, and it gives me can not load schedule database, however it sees the group, just doesnt load it.

Is there any special boxed to check or anything of the sort to bring it in to Expedition?

Thanks
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top