P3 Schedule error into Expedition

Status
Not open for further replies.

kinjor

Technical User
Mar 30, 2005
1
0
0
US
I am trying to link a P3 schedule with Primavera Expedition, and it gives me can not load schedule database, however it sees the group, just doesnt load it.

Is there any special boxed to check or anything of the sort to bring it in to Expedition?

Thanks
 