How do I create a microsoft project plan where the start date equals 7 weeks from the end date each time. I want to be able to enter an end date and then they first task begins 7 weeks earlier then that date.
You can schedule from a project finish date in Project by changing the "Schedule from" in Project Information to "Finish date". As to the 7 weeks - why seven? Does the task take 7 weeks to complete? If so, set the task duration to 7 weeks and the start will be calculated. That being said - a single task with a 7 week duration is a bit long. I suggest assessing your level of detail in the WBS and revising.
I would also set a milestone last task for your end date and place a "Must Finish On" constraint. Whether the end date is indeed moveable is not as importand as forcing earlier tasks to line up. You might also want to have a milestone "Must Start On" first task. This will force everything within those two boundaries.
==================================
The trouble with doing something right the first time is that nobody appreciates how difficult it was - Steven Wright
One additional question regarding the 7 weeks. Is that seven calendar weeks? Or 49 days? Or 35 working days? These are important considerations and can be somewhat controlled using the Project Calendar. HTH.
==================================
The trouble with doing something right the first time is that nobody appreciates how difficult it was - Steven Wright
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.