YANKRAY
Technical User
- Nov 7, 2003
- 283
Excel 2003.
I am trying to determine number of work days per month for a projects duration.
For Example: Project Starts 6 Jun 2007, Project Ends 21 December 2007.
Is there a formula I can use that will put the network days under the column or row heading for the month? The result would look like this:
May 07 0
Jun 07 4
Jul 07 22
Aug 07 23
Sep 07 20
Oct 07 23
Nov 07 22
Dec 07 10 (Only 10 work days because the date of the report is the 10th so work days 3-7 are already past). The current month should always be the remaining work days.
Jan 08 0
I will use a seperate spreadsheet to record holidays for 2007, 2008, 2009, etc.
Thanks,
Ray
I am trying to determine number of work days per month for a projects duration.
For Example: Project Starts 6 Jun 2007, Project Ends 21 December 2007.
Is there a formula I can use that will put the network days under the column or row heading for the month? The result would look like this:
May 07 0
Jun 07 4
Jul 07 22
Aug 07 23
Sep 07 20
Oct 07 23
Nov 07 22
Dec 07 10 (Only 10 work days because the date of the report is the 10th so work days 3-7 are already past). The current month should always be the remaining work days.
Jan 08 0
I will use a seperate spreadsheet to record holidays for 2007, 2008, 2009, etc.
Thanks,
Ray