Hello All - I could use some expert advice relative to best practices for scheduling certain types of activities/tasks in MS Project:
1. How can I schedule activities/tasks which are parallel to critical activities/tasks in terms of timing but are not on the main critical path?
Example - Tasks A, B, C, E, F are on the critical path. Task D is parallel to Task E (i.e., start date is the same) but is not dependent on Task C nor is it a predecessor to Tasks E or F. What's the best way to schedule Task D?
One thought I had was to simply link Task D as a successor to the project start milestone and just add sufficient lag time so that it starts on the desired date but I'm not sure that's the best approach - another obvious solution would be to hard-code the start date for Task D but again, not sure that's the best approach.
2. What's the best way to schedule administrative or project management-type activities/tasks that will need to be performed throughout the project but which are not part of the actual project work content or critical path per se?
Examples - Meetings, risk management activities, planning activities, budgeting activities, etc.
Thanks in advance for any advice/guidance you can offer on these two questions.
1. How can I schedule activities/tasks which are parallel to critical activities/tasks in terms of timing but are not on the main critical path?
Example - Tasks A, B, C, E, F are on the critical path. Task D is parallel to Task E (i.e., start date is the same) but is not dependent on Task C nor is it a predecessor to Tasks E or F. What's the best way to schedule Task D?
One thought I had was to simply link Task D as a successor to the project start milestone and just add sufficient lag time so that it starts on the desired date but I'm not sure that's the best approach - another obvious solution would be to hard-code the start date for Task D but again, not sure that's the best approach.
2. What's the best way to schedule administrative or project management-type activities/tasks that will need to be performed throughout the project but which are not part of the actual project work content or critical path per se?
Examples - Meetings, risk management activities, planning activities, budgeting activities, etc.
Thanks in advance for any advice/guidance you can offer on these two questions.