Need for: Work = Duration

Status
Not open for further replies.

nic2024

Technical User
May 14, 2009
1
US
We have tasks that we're giving a set 80 hours to complete. This task will be completed in 80 hours no matter how many people are working on this task (which will fluctuate). Is there a setting that can make WORK = DURATION despite how many resources are assigned?!


 
Based on the wording of your question: you cannot do what you have asked.

Based on the background you supplied: look at help for the field "Effort Driven
 